[Vietnam’s first nuclear power plant may be delayed until 2037 and the risk of power shortages rises] November 26th, Vietnam’s first nuclear power plant may be forced to postpone its operation until after 2037, which will make the country’s efforts to strengthen energy security and promote economic growth face greater challenges. According to the revised draft of Vietnam’s power development plan released this week for comments, Vietnam’s Ministry of Industry and Trade proposed that the Ninh Thuan 1 nuclear power plant is expected to be put into operation in 2037-2038, and the Ninh Thuan 2 nuclear power plant is expected to be put into operation in 2039-2040, which is later than the current planning requirement for the two nuclear power plants to be put into operation between 2030 and 2035.