[The main project of Unit 2 of the Zhaoyuan Nuclear Power Project has started] September 5th, this morning, Unit 2 of the CGN Shandong Zhaoyuan Nuclear Power Project started pouring the first concrete tank of the nuclear island, marking the official start of the main project of the unit and the first phase of the project entering the comprehensive construction stage. According to reports, the total amount of concrete poured for Unit 2, which is under construction this time, is about 8,800 cubic meters, which is equivalent to the volume of 3.5 standard swimming pools. The entire unit is poured at 7 points. The continuous pouring is completed in one go. It is expected that the entire concrete will take about 60 hours. The main project of Unit 1 of this project started on November 18, 2025. (CCTV News)