According to the Financial Times report, major server manufacturers such as Dell, HPE, Lenovo and Super Micro were accused of significantly raising the final selling price within months after reaching a preliminary agreement with customers on the purchase price of AI servers. The price increase for some orders is said to be as high as 25%, 30%, or even 45%, but customers often have no choice but to accept it because the demand for computing hardware in data center construction is extremely urgent.

The report quoted multiple people familiar with the matter as saying that this price change is not an isolated phenomenon, but is gradually becoming a "standard" practice in the data center industry. Customers typically only get a rough base price when signing up, with the expectation that before servers, racks and other hardware are delivered, the actual bill may be significantly higher than the originally agreed-upon amount.

Affected are not only large cloud service providers, but also financial institutions active in algorithmic trading and electronic market making. Institutions mentioned in the report include important players in the trading industry such as Jane Street, Optiver and Hudson River Trading. These enterprises require a large number of high-performance servers to support low-latency transactions, model training and data analysis, and are therefore highly dependent on the supply of AI servers.

One source said that suppliers often propose price increases during the months-long manufacturing cycle, and there can be a "significant difference" between the final price and the original amount. The person also said that he has never refused such price increases because "in the final analysis, computing power is valuable to us and we are willing to pay for it."

Currently, no relevant company has publicly confirmed or denied whether this temporary price increase has become common in the AI ​​data center industry. The companies mentioned in the report have not issued official statements on the matter. However, the controversy surrounding the price hike has triggered legal battles.

In June this year, XTX Markets, a UK-based algorithmic trading company, sued Dell, accusing the latter of requiring a substantial increase in delivery fees even after the two parties had agreed on a fixed price and paid an additional $5 million to lock in the price. Dell then allegedly required XTX to pay an additional $62 million to $70 million to deliver the relevant servers.

Dell told XTX executives that the price increase is to cover the rising cost of memory chips, and the company cannot absorb this part of the expenditure through other means. XTX is currently building a new data center in Finland, but this ongoing lawsuit could have a major impact on the project.

This incident highlights the supply chain pressure behind the AI ​​infrastructure boom. As global companies accelerate the construction of data centers and purchase GPU servers and high-speed network equipment, the tight supply of key components, rising costs and limited production capacity are giving server manufacturers a stronger position in negotiations. For buyers, even if they have signed a contract, it is difficult to completely avoid the risk of price readjustment.